Example data

Site A, Columbus OH

Site readiness report · Operating capacity + planned expansion

Interconnection status

AEP Ohio / PJM

Expansion in study
Requested
120 MW
Approved / operating
90 MW
Expansion in review
30 MW
✓ApplicationRecorded
02Expansion studyIn progress
03AmendmentPending study
04EnergizationConditional
Example evidence: service agreement on file · Expansion study scope received.

Tariff obligations

AEP Ohio data-center tariff · Site-specific review

2 need action
ObligationRequired evidenceStatus
Demand billingVerify ratchet and tiered minimum.Model pending
Ramp and service termDocument load ramp and term exposure.Schedule needed
Credit supportCredit review and security record.Evidence on file
Exit and cancellationTrack notice and cost obligations.Review recorded
Track the executed contract and effective tariff together. Flexibility does not remove billing obligations.
78OF 100
Site readiness

Close the evidence gap.

Operations established.
Expansion evidence under review.

Illustrative weighted score.
Not a utility approval or a power guarantee.
Connection25/30
Metering24/25
Tariff17/25
Response12/20

Open gaps

Next actions for Site A

3 open
  • Approve the revised load ramp

    Energy manager · Needed for tariff model

    Due 12 Nov 2026
  • Sign off the expansion one-line

    Site engineer · Needed for study inputs

    Due 18 Nov 2026
  • Accept response-test evidence

    Program reviewer · Metering method pending

    Due 24 Nov 2026

Estimated expansion timeline

Planning estimate, subject to study and equipment delivery

Additional 30 MW
NOV 2026

Confirm load ramp
and study inputs

Q1 2027

Complete study
and service amendment

Q2 2027

Utility works and
equipment allocation

Q3 2027 · Target

Conditional energization.
Utility date not confirmed.