Site A, Columbus OH
Site readiness report · Operating capacity + planned expansion
Interconnection status
AEP Ohio / PJM
Requested
120 MW
Approved / operating
90 MW
Expansion in review
30 MW
✓ApplicationRecorded
02Expansion studyIn progress
03AmendmentPending study
04EnergizationConditional
Example evidence: service agreement on file · Expansion study scope received.
Tariff obligations
AEP Ohio data-center tariff · Site-specific review
| Obligation | Required evidence | Status |
|---|---|---|
| Demand billing | Verify ratchet and tiered minimum. | Model pending |
| Ramp and service term | Document load ramp and term exposure. | Schedule needed |
| Credit support | Credit review and security record. | Evidence on file |
| Exit and cancellation | Track notice and cost obligations. | Review recorded |
Track the executed contract and effective tariff together. Flexibility does not remove billing obligations.
78OF 100
Site readiness
Close the evidence gap.
Operations established.
Expansion evidence under review.
Illustrative weighted score.
Not a utility approval or a power guarantee.
Not a utility approval or a power guarantee.
Connection25/30
Metering24/25
Tariff17/25
Response12/20
Open gaps
Next actions for Site A
Approve the revised load ramp
Energy manager · Needed for tariff model
Due 12 Nov 2026Sign off the expansion one-line
Site engineer · Needed for study inputs
Due 18 Nov 2026Accept response-test evidence
Program reviewer · Metering method pending
Due 24 Nov 2026
Estimated expansion timeline
Planning estimate, subject to study and equipment delivery
NOV 2026
Confirm load ramp
and study inputs
Q1 2027
Complete study
and service amendment
Q2 2027
Utility works and
equipment allocation
Q3 2027 · Target
Conditional energization.
Utility date not confirmed.